Project Details

CONSTRUCTION OF TRANS CARGO GO-DOWN

Project: General Earthworks: Site clearance, Excavation Works, Back-filling of materials, Fill of Gravel material
Location: Tabata, Dar es Salaam
Client: Italframe Ltd
Contract Value: TSH 450,000,000
Area Covered: 2 Acres
Year Completed: Ongoing
Expertise: Civil Works
Summary: During the beginning of this project, We began establishing a name due to our large number of earthmoving equipments and trucks. Italframe, gladly called us to tackle the earthwork problems for there highly anticipated 2 storey Godown project. We excavated 2 m of just under 2 acres of land to allow for Concrete columns to be set. After setting we filled back carefully 2m of material taking good care not to damage the columns, and a further 90 cm of imported fill material to achieve 98% Compaction. Osaka also, excavated some water tanks, and drainage systems for the project.